Huge Illinois Rubblization Project Completed Early

Antigo Construction completed 263,000 square yards (37 lane miles) of concrete rubblization in only 14 days on I-70 in Clark County, Illinois. The joint venture of Howell Asphalt Company and Champaign Asphalt Company paved 550,000 tons of asphalt. The eastbound lanes were reopened 26 days ahead of schedule and the westbound lanes were reopened 43 days ahead of schedule on September 8, 2003. For more information see Asphalt Institute article or Howell Asphalt Company testimonial.

2 MHBs completing the last lane of rubblizing.


Test hole showing rebar debonded from concrete.


Paving first lift of asphalt over rubblized concrete.


Completed project.


Home | Rubblizing | Cracking & Seating | Breaking for Removal | Breaker Specifications & Capabilities

Antigo Construction, Inc. Profile | Contact Info | Testimonials | News Archive

                   Copyright © 2002, Antigo Construction, Inc. All rights reserved.