| 8600 / T8600 Badger Breaker® |
| 1. |
Production rates up to 3,000 sq. yds. per hour per breaker on typical 9-inch thick crack and seat projects. |
| 2. |
Production rates of up to 1,000 sq. yds. per hour per breaker when breaking 10-to 12-inch thick pavement, either plain or mesh-reinforced, into 24-inch minus pieces. |
| 3. |
Production rate of 400 sq. yds. per hour per breaker when pulverizing 10-inch thick continuously reinforced concrete pavement (CRCP) to the point where the rebar is completely free of the pavement and ready to be lifted out prior to pavement removal. |
| 4. |
Break concrete pavement as much as 36-inches thick. |
| 5. |
Successfully crack or break concrete pavement through asphalt overlays up to 12-inches thick. |
| 6. |
Crack thick, over 8 inches, asphalt pavement or asphalt over concrete for easier ripping, smaller pieces and more efficient removal. |
MHB Badger Breaker®
|
| 1. |
Rubblize 8- to 10-inch thick pavement up to 13-feet wide per pass for an average of 1 lane mile per MHB per 10-hour shift. |
| 2. |
Rubblize 14-inch thick pavement as above at the rate of 1 lane mile per MHB per 12-hour shift. |
| 3. |
Selectively break pavement sections without damaging adjoining sections which are to remain. |
| 4. |
Break close to structures and over underground utilities due to low vibration level of lightweight hammers. |
| 5. |
Production rates of 2 to 3 lane miles per MHB per shift when breaking to 24-inch minus removal specification. |
| 6. |
Crack, break, or rubblize concrete pavement over cement treated base (CTB) without damaging the CTB. |